# CompTIA Project+ PK0-005 practice exams

> Prepare for PK0-005 with 440 practice questions across 5 full timed exams, weighted toward Project Management Concepts. Every answer is explained.

Page: https://devopscodelab.com/exams/comptia-pk0-005/

440 questions in 5 timed practice tests. Each test has about 90 questions and a 90-minute limit. The pass mark is 79%. Results are split across the 4 exam domains.

## Exam at a glance

| Setting | Value |
| --- | --- |
| Practice tests | 5 |
| Questions in total | 440 |
| Questions per test | About 90 |
| Time limit per test | 90 minutes |
| Pass mark | 79% |
| Question types | Single answer and multiple answer (43 multiple-answer questions) |
| Level | Associate |
| Category | Project Management & Agile |

These are the settings of our practice tests. Check the official CompTIA exam page for the current format before you book.

## Domains and weights

| Domain | Weight | Questions in our bank |
| --- | --- | --- |
| Project Management Concepts | 33% | 146 |
| Project Life Cycle Phases | 30% | 132 |
| Tools and Documentation | 19% | 84 |
| Basics of IT and Governance | 18% | 78 |

## Price and access

- PK0-005 practice exams: $12.99 for 12 months of access.
- Free mini exam: 15 questions with explanations (free account): https://devopscodelab.com/app/exams/comptia-pk0-005/mini/
- All-Access subscription includes every exam: https://devopscodelab.com/pricing/
- 10 free questions with answers: https://devopscodelab.com/exams/comptia-pk0-005/free-practice-questions/

## Sample questions

### Question 1 of 3

A stakeholder emails the project manager asking to add a reporting dashboard to an approved CRM rollout. What should the project manager do FIRST?

- A. Ask the development team to estimate and start the dashboard work in the next sprint
- B. Forward the request to the sponsor and ask for an immediate yes-or-no decision
- C. Log the request and assess its impact on scope, schedule, and cost
- D. Decline the request because the scope baseline has already been approved

**Answer:** C

**Explanation:** Every change request is first documented in the change log and then analyzed for impact before anyone decides on it. Starting the work skips approval entirely, asking the sponsor for a decision without an impact assessment gives them nothing to decide on, and rejecting it outright ignores that approved baselines can legitimately change through change control.

### Question 2 of 3

The change control board approved a request that adds two weeks to a network refresh project. Which action should the project manager take NEXT?

- A. Update the schedule baseline and communicate the change to affected stakeholders
- B. Record the approval in the lessons learned register for review at project closure
- C. Submit a second change request so the quality team can verify the new end date
- D. Leave the baseline unchanged and track the two weeks as a schedule variance

**Answer:** A

**Explanation:** After approval, the PM updates the affected baselines and project documents and tells stakeholders what changed. Lessons learned are not the place to implement a change, a second change request for the same item adds pointless bureaucracy, and leaving the baseline unchanged would report an approved change as if it were a performance problem.

### Question 3 of 3 (choose 2)

Which roles typically sit on a project's change control board? (Choose two.)

- A. The vendor account manager who sold the tool
- B. Key stakeholders affected by changes
- C. Testers who execute the system test cases
- D. The project sponsor or a delegate
- E. Every end user of the final product

**Answer:** B, D

**Explanation:** Change control boards usually include the sponsor or delegate and key stakeholders with authority over scope, cost, and schedule. All end users would make the board unmanageable, testers provide input on impact but do not hold decision authority, and a vendor's account manager has a commercial interest and no governance role.


## Study plans

### Two weeks

1. Day 1: take practice test 1 in exam mode to get a baseline.
2. Days 2 to 5: domain mode on Project Management Concepts and Project Life Cycle Phases, the two most heavily weighted domains.
3. Day 6: practice test 2 in exam mode, then the mistakes quiz.
4. Days 7 to 12: practice tests 3 to 5, one every other day, each followed by its mistakes quiz.
5. Days 13 and 14: final mode. Book the exam when your readiness stays above the pass mark.

### Four weeks

1. Week 1: one practice test in practice mode, reading every explanation. Note your two lowest domains.
2. Week 2: domain mode on those two domains, then a second practice test in exam mode.
3. Week 3: practice tests 3 and 4 in exam mode, with the mistakes and flagged quizzes after each.
4. Week 4: practice test 5 and final mode until your readiness holds above the pass mark.

## Questions about the PK0-005 practice exams

**Are these real PK0-005 exam questions?**

No. We write every question ourselves and map it to the published PK0-005 exam objectives. We do not use leaked or recalled questions.

**Do the time limit and pass mark match the official exam?**

They match the settings of our practice tests. Exam providers change their format from time to time, so check the official exam page before you book.

**Can I try it before I pay?**

Yes. The free mini exam has 15 questions with full explanations and needs no account.

**How long do I keep access?**

A single-exam purchase gives you 12 months of access. All-Access includes this exam for as long as your subscription runs.

**What happens after I finish a test?**

You get a score, a pass or fail against the pass mark, a score per domain and every answer with its explanation.

Last updated November 2026.

DevOpsCode Lab is not affiliated with CompTIA. PK0-005 and related names are trademarks of their owners. We write every question ourselves; these are not real exam questions.