### Question 1 of 10

A stakeholder emails the project manager asking to add a reporting dashboard to an approved CRM rollout. What should the project manager do FIRST?

- A. Ask the development team to estimate and start the dashboard work in the next sprint
- B. Forward the request to the sponsor and ask for an immediate yes-or-no decision
- C. Log the request and assess its impact on scope, schedule, and cost
- D. Decline the request because the scope baseline has already been approved

**Answer:** C

**Explanation:** Every change request is first documented in the change log and then analyzed for impact before anyone decides on it. Starting the work skips approval entirely, asking the sponsor for a decision without an impact assessment gives them nothing to decide on, and rejecting it outright ignores that approved baselines can legitimately change through change control.

### Question 2 of 10

The change control board approved a request that adds two weeks to a network refresh project. Which action should the project manager take NEXT?

- A. Update the schedule baseline and communicate the change to affected stakeholders
- B. Record the approval in the lessons learned register for review at project closure
- C. Submit a second change request so the quality team can verify the new end date
- D. Leave the baseline unchanged and track the two weeks as a schedule variance

**Answer:** A

**Explanation:** After approval, the PM updates the affected baselines and project documents and tells stakeholders what changed. Lessons learned are not the place to implement a change, a second change request for the same item adds pointless bureaucracy, and leaving the baseline unchanged would report an approved change as if it were a performance problem.

### Question 3 of 10 (choose 2)

Which roles typically sit on a project's change control board? (Choose two.)

- A. The vendor account manager who sold the tool
- B. Key stakeholders affected by changes
- C. Testers who execute the system test cases
- D. The project sponsor or a delegate
- E. Every end user of the final product

**Answer:** B, D

**Explanation:** Change control boards usually include the sponsor or delegate and key stakeholders with authority over scope, cost, and schedule. All end users would make the board unmanageable, testers provide input on impact but do not hold decision authority, and a vendor's account manager has a commercial interest and no governance role.

### Question 4 of 10

A software release passed all system tests, but during user acceptance testing, business users say a report does not match how the finance team actually closes the month. What does this MOST likely indicate?

- A. The system test cases were executed in the wrong environment by the testers
- B. The development team failed to follow the organization's secure coding and review standards
- C. Requirements were not validated with the right business stakeholders
- D. The change control board approved too many changes during the execution phase

**Answer:** C

**Explanation:** Passing system tests but failing UAT usually means the product matches the documented requirements, but those requirements did not reflect real business needs, which points to poor validation with the right stakeholders. The wrong test environment, coding standards, and change approvals would not explain a mismatch with how finance actually works.

### Question 5 of 10

A project manager realizes during execution that one approved requirement conflicts with a new company security standard. What is the BEST next step?

- A. Ask the security team to grant a permanent exception without assessing the risk
- B. Document the conflict and raise a change request to align the requirement with the standard
- C. Build the requirement as approved because the scope baseline takes precedence over standards
- D. Remove the requirement from the solution without informing the business owner

**Answer:** B

**Explanation:** Conflicts between approved scope and organizational policy should be documented and resolved through change control, usually by updating the requirement. Building something non-compliant creates risk, silent removal skips stakeholders, and permanent exceptions without assessment undermine security governance.

### Question 6 of 10

A client wants a vendor to start work immediately on a data migration whose total scope is unclear. The client wants to pay only for the hours actually worked. Which contract type fits BEST?

- A. Time and materials
- B. Cost plus award fee
- C. Firm fixed price
- D. Fixed price incentive fee

**Answer:** A

**Explanation:** Time and materials contracts pay for actual hours and materials at agreed rates, which suits unclear scope and quick starts. Fixed price contracts require well-defined scope, an incentive fee adds performance targets on a fixed price, and cost-plus contracts reimburse costs plus a fee, which is more administrative than paying hourly rates.

### Question 7 of 10

Auditors ask a project team to prove that every approved requirement for a payroll system was designed, built, and tested. Which document provides this traceability?

- A. Quality management plan with test strategy
- B. Requirements traceability matrix
- C. Project charter
- D. Work breakdown structure

**Answer:** B

**Explanation:** A requirements traceability matrix links each requirement to its source, design elements, and test cases through the life cycle. The WBS decomposes deliverables but does not trace requirements to tests, the charter is high-level, and the quality management plan describes how testing will be done rather than proving each requirement was covered.

### Question 8 of 10 (choose 2)

A project manager must choose a collaboration platform for a project with external contractors. Which requirements should take priority? (Choose two.)

- A. Built-in polls and reactions to make team discussions more engaging
- B. Support for guest access with permissions limited to project content
- C. The lowest per-user price, even if guest access must be shared
- D. Compliance with the organization's security and data retention policies
- E. Ability for any user to delete any file without leaving a version history

**Answer:** B, D

**Explanation:** Controlled guest access and compliance with security and retention policies protect data while enabling collaboration with contractors. Polls and reactions are nice-to-have features, choosing on price alone when guest access must be shared weakens accountability, and unrestricted deletion without history creates data loss and audit risks.

### Question 9 of 10

Which statement BEST describes the shared responsibility model in cloud computing?

- A. The provider secures the infrastructure; the customer secures its data, access, and configuration
- B. The provider and the customer each pay half of the cost of every security incident that occurs
- C. The provider is fully responsible for all security, including customer data and user access settings
- D. The customer is fully responsible for all security, including the physical data center facilities

**Answer:** A

**Explanation:** Under shared responsibility, the provider secures the cloud infrastructure while the customer secures its data, identities, and configurations, with the split depending on the service model. The provider is not responsible for everything, the customer does not secure physical facilities, and the model is about duties rather than splitting costs.

### Question 10 of 10

A bank plans to roll out new teller software to one branch, evaluate the results for two weeks, and then roll it out to all other branches. Which deployment approach is this?

- A. Blue-green deployment
- B. Big bang deployment
- C. Parallel deployment
- D. Pilot deployment

**Answer:** D

**Explanation:** A pilot deploys to a small group first to validate the solution before a wider rollout. A big bang deployment switches everyone at once, a parallel deployment runs old and new systems side by side for the same users, and blue-green switches traffic between two identical production environments.