# PMI Assoc. in Project Management (CAPM) practice exams

> CAPM practice exams: 440 questions in 5 timed tests covering Project Management Fundamentals. Every answer explained, with a score for each domain.

Page: https://devopscodelab.com/exams/pmi-capm/

440 questions in 5 timed practice tests. Each test has about 90 questions and a 108-minute limit. The pass mark is 70%. Results are split across the 4 exam domains.

## Exam at a glance

| Setting | Value |
| --- | --- |
| Practice tests | 5 |
| Questions in total | 440 |
| Questions per test | About 90 |
| Time limit per test | 108 minutes |
| Pass mark | 70% |
| Question types | Single answer and multiple answer (41 multiple-answer questions) |
| Level | Associate |
| Category | Project Management & Agile |

These are the settings of our practice tests. Check the official PMI exam page for the current format before you book.

## Domains and weights

| Domain | Weight | Questions in our bank |
| --- | --- | --- |
| Project Management Fundamentals and Core Concepts | 36% | 159 |
| Predictive, Plan-Based Methodologies | 17% | 74 |
| Agile Frameworks/Methodologies | 20% | 88 |
| Business Analysis Frameworks | 27% | 119 |

## Price and access

- CAPM practice exams: $12.99 for 12 months of access.
- Free mini exam: 15 questions with explanations (free account): https://devopscodelab.com/app/exams/pmi-capm/mini/
- All-Access subscription includes every exam: https://devopscodelab.com/pricing/
- 10 free questions with answers: https://devopscodelab.com/exams/pmi-capm/free-practice-questions/

## Sample questions

### Question 1 of 3

A software company's project to launch a mobile app has a well-understood back-end migration and a highly uncertain customer-facing interface. The team plans the migration in detail upfront but builds the interface in short iterations with user feedback. What is this approach called?

- A. A hybrid approach that combines predictive and adaptive elements
- B. A predictive approach with rolling-wave planning for every component
- C. An incremental approach where all deliverables are released at the end
- D. A purely adaptive approach because some work is done in iterations

**Answer:** A

**Explanation:** Using predictive planning for stable work and adaptive iterations for uncertain work within the same project is a hybrid approach. Rolling-wave planning is a predictive technique for progressively elaborating later work, but it does not describe iterative user-feedback cycles. Incremental delivery provides usable parts over time rather than all at the end, and a purely adaptive approach would not plan the migration in full detail upfront.

### Question 2 of 3

A logistics firm's steering committee approved funding for a warehouse automation initiative last week. The newly assigned project manager wants confirmation, in writing, of the high-level objectives, the summary milestones, and her authority to request staff from other departments. Which artifact should the sponsor issue?

- A. The project management plan
- B. The approved business case
- C. The project charter
- D. The resource management plan

**Answer:** C

**Explanation:** The charter records high-level objectives, summary milestones, and the project manager's authority, and it is issued by the sponsor. The project management plan is developed later by the project manager and team. The resource management plan explains how resources will be acquired and managed but does not grant authority, and the business case justifies the investment rather than authorizing the project manager.

### Question 3 of 3

A project team is choosing between a predictive and an adaptive life cycle for a regulatory reporting system. Requirements are fixed by law, published in detail, and unlikely to change before the deadline. Which life cycle is MOST suitable?

- A. A predictive life cycle, because the scope is well defined and stable at the start
- B. An adaptive life cycle, because short iterations always lower total project cost
- C. An iterative life cycle, because requirements must be discovered through prototypes
- D. An incremental life cycle, because each release must be approved by the regulator

**Answer:** A

**Explanation:** Predictive life cycles work best when scope, time, and cost can be determined early because requirements are clear and stable, as with published regulations. Short iterations do not automatically lower cost and add little value when nothing is expected to change. Prototyping to discover requirements is unnecessary when they are already published, and nothing indicates the regulator approves partial releases.


## Study plans

### Two weeks

1. Day 1: take practice test 1 in exam mode to get a baseline.
2. Days 2 to 5: domain mode on Project Management Fundamentals and Core Concepts and Business Analysis Frameworks, the two most heavily weighted domains.
3. Day 6: practice test 2 in exam mode, then the mistakes quiz.
4. Days 7 to 12: practice tests 3 to 5, one every other day, each followed by its mistakes quiz.
5. Days 13 and 14: final mode. Book the exam when your readiness stays above the pass mark.

### Four weeks

1. Week 1: one practice test in practice mode, reading every explanation. Note your two lowest domains.
2. Week 2: domain mode on those two domains, then a second practice test in exam mode.
3. Week 3: practice tests 3 and 4 in exam mode, with the mistakes and flagged quizzes after each.
4. Week 4: practice test 5 and final mode until your readiness holds above the pass mark.

## Questions about the CAPM practice exams

**Are these real CAPM exam questions?**

No. We write every question ourselves and map it to the published CAPM exam objectives. We do not use leaked or recalled questions.

**Do the time limit and pass mark match the official exam?**

They match the settings of our practice tests. Exam providers change their format from time to time, so check the official exam page before you book.

**Can I try it before I pay?**

Yes. The free mini exam has 15 questions with full explanations and needs no account.

**How long do I keep access?**

A single-exam purchase gives you 12 months of access. All-Access includes this exam for as long as your subscription runs.

**What happens after I finish a test?**

You get a score, a pass or fail against the pass mark, a score per domain and every answer with its explanation.

Last updated November 2026.

DevOpsCode Lab is not affiliated with PMI. CAPM and related names are trademarks of their owners. We write every question ourselves; these are not real exam questions.