# Free CAPM practice questions

> 10 free CAPM practice questions with the correct answer and an explanation.

Page: https://devopscodelab.com/exams/pmi-capm/free-practice-questions/
Practice exams: https://devopscodelab.com/exams/pmi-capm/

### Question 1 of 10

A software company's project to launch a mobile app has a well-understood back-end migration and a highly uncertain customer-facing interface. The team plans the migration in detail upfront but builds the interface in short iterations with user feedback. What is this approach called?

- A. A hybrid approach that combines predictive and adaptive elements
- B. A predictive approach with rolling-wave planning for every component
- C. An incremental approach where all deliverables are released at the end
- D. A purely adaptive approach because some work is done in iterations

**Answer:** A

**Explanation:** Using predictive planning for stable work and adaptive iterations for uncertain work within the same project is a hybrid approach. Rolling-wave planning is a predictive technique for progressively elaborating later work, but it does not describe iterative user-feedback cycles. Incremental delivery provides usable parts over time rather than all at the end, and a purely adaptive approach would not plan the migration in full detail upfront.

### Question 2 of 10

A logistics firm's steering committee approved funding for a warehouse automation initiative last week. The newly assigned project manager wants confirmation, in writing, of the high-level objectives, the summary milestones, and her authority to request staff from other departments. Which artifact should the sponsor issue?

- A. The project management plan
- B. The approved business case
- C. The project charter
- D. The resource management plan

**Answer:** C

**Explanation:** The charter records high-level objectives, summary milestones, and the project manager's authority, and it is issued by the sponsor. The project management plan is developed later by the project manager and team. The resource management plan explains how resources will be acquired and managed but does not grant authority, and the business case justifies the investment rather than authorizing the project manager.

### Question 3 of 10

A project team is choosing between a predictive and an adaptive life cycle for a regulatory reporting system. Requirements are fixed by law, published in detail, and unlikely to change before the deadline. Which life cycle is MOST suitable?

- A. A predictive life cycle, because the scope is well defined and stable at the start
- B. An adaptive life cycle, because short iterations always lower total project cost
- C. An iterative life cycle, because requirements must be discovered through prototypes
- D. An incremental life cycle, because each release must be approved by the regulator

**Answer:** A

**Explanation:** Predictive life cycles work best when scope, time, and cost can be determined early because requirements are clear and stable, as with published regulations. Short iterations do not automatically lower cost and add little value when nothing is expected to change. Prototyping to discover requirements is unnecessary when they are already published, and nothing indicates the regulator approves partial releases.

### Question 4 of 10

A project manager reviews the WBS and finds a work package called "Configure reporting" that two teams interpret differently. Which document should provide detailed information about the work package, including its description, acceptance criteria, and responsible organization?

- A. Activity list
- B. Project scope statement
- C. Requirements management plan
- D. WBS dictionary

**Answer:** D

**Explanation:** The WBS dictionary provides detailed deliverable, activity, and scheduling information for each WBS component, including description, acceptance criteria, and responsible organization. The scope statement describes overall project scope, the requirements management plan describes how requirements are handled, and the activity list lists schedule activities without full work package details.

### Question 5 of 10

A project has a budget at completion of 500,000 USD, earned value of 200,000 USD, and actual cost of 250,000 USD. If current cost performance is expected to continue, what is the estimate at completion (EAC)?

- A. 550,000 USD
- B. 625,000 USD
- C. 400,000 USD
- D. 450,000 USD

**Answer:** B

**Explanation:** The cost performance index is EV divided by AC, or 0.8, and when current performance is expected to continue EAC equals BAC divided by CPI, giving 625,000 USD. Adding the cost overrun to BAC gives 550,000 USD, which assumes future work at planned rates. The other two figures result from multiplying instead of dividing by CPI or misreading the variance.

### Question 6 of 10

A product team builds the simplest version of a meal-planning app that lets early users create a weekly plan, so the team can learn whether people will actually use it before investing further. What is this version called?

- A. Minimum marketable feature
- B. Minimum viable product
- C. Proof of concept prototype
- D. Release candidate

**Answer:** B

**Explanation:** A minimum viable product is the smallest version that allows the team to validate learning about customers with the least effort. A minimum marketable feature is the smallest piece of functionality that delivers value customers will pay for or use. A proof of concept tests technical feasibility rather than market demand, and a release candidate is a build that is nearly ready for production.

### Question 7 of 10

A marketing department's VP tells the Scrum team that her campaign feature must be built before the analytics dashboard that the team had planned next. The Developers are unsure whose decision this is. According to the Scrum Guide, who decides the order of the Product Backlog?

- A. The Product Owner, who may represent the VP's needs but makes the final ordering decision
- B. The Scrum Master, who facilitates the conflict and chooses the fairest order
- C. The Developers, who decide based on technical dependencies between the items
- D. The VP, because senior stakeholders outrank team members on product decisions

**Answer:** A

**Explanation:** The Product Owner is one person, not a committee, and is accountable for ordering the Product Backlog; others who want changes must convince the Product Owner. The VP is a stakeholder and cannot override that accountability. The Scrum Master helps the team and organization use Scrum but does not order the backlog, and Developers advise on dependencies without owning the ordering.

### Question 8 of 10

Which type of requirement describes the conditions and capabilities needed to move from the current state to the future state, such as data conversion and user training, and is no longer needed once the solution is in place?

- A. Transition requirements
- B. Non-functional requirements
- C. Business requirements
- D. Stakeholder requirements

**Answer:** A

**Explanation:** Transition requirements are temporary capabilities, such as data conversion and training, needed to move to the future state. Non-functional requirements describe quality attributes of the solution, such as performance or security. Stakeholder requirements capture needs of particular stakeholders, and business requirements describe high-level organizational needs and goals.

### Question 9 of 10

A product team has more requested features than it can deliver in the first release. The business analyst asks stakeholders to classify each feature as Must have, Should have, Could have, or Won't have this time. Which technique is being used?

- A. MoSCoW prioritization
- B. Kano analysis
- C. Weighted shortest job first
- D. Purchase a feature

**Answer:** A

**Explanation:** MoSCoW categorizes requirements into Must, Should, Could, and Won't have this time. Kano analysis classifies features by their effect on customer satisfaction, such as basic, performance, and delighter features. Purchase a feature gives stakeholders play money to spend, and weighted shortest job first ranks work by cost of delay divided by job size.

### Question 10 of 10

A business analyst is writing requirements for a hotel booking system. One requirement says "The system shall allow guests to cancel a booking up to 24 hours before arrival without charge." How is this requirement classified?

- A. Transition requirement
- B. Non-functional requirement
- C. Project requirement
- D. Functional requirement

**Answer:** D

**Explanation:** The requirement describes a behavior the solution must perform, so it is functional. Non-functional requirements describe qualities such as performance or security, transition requirements are temporary needs for moving to the new solution, and project requirements describe actions or conditions the project must meet rather than solution behavior.