Question 1 of 10, Project Management Concepts
A stakeholder emails the project manager asking to add a reporting dashboard to an approved CRM rollout. What should the project manager do FIRST?
- AAsk the development team to estimate and start the dashboard work in the next sprint
- BForward the request to the sponsor and ask for an immediate yes-or-no decision
- CLog the request and assess its impact on scope, schedule, and cost Correct answer
- DDecline the request because the scope baseline has already been approved
Answer and explanation: Every change request is first documented in the change log and then analyzed for impact before anyone decides on it. Starting the work skips approval entirely, asking the sponsor for a decision without an impact assessment gives them nothing to decide on, and rejecting it outright ignores that approved baselines can legitimately change through change control.
Question 2 of 10, Project Management Concepts
The change control board approved a request that adds two weeks to a network refresh project. Which action should the project manager take NEXT?
- AUpdate the schedule baseline and communicate the change to affected stakeholders Correct answer
- BRecord the approval in the lessons learned register for review at project closure
- CSubmit a second change request so the quality team can verify the new end date
- DLeave the baseline unchanged and track the two weeks as a schedule variance
Answer and explanation: After approval, the PM updates the affected baselines and project documents and tells stakeholders what changed. Lessons learned are not the place to implement a change, a second change request for the same item adds pointless bureaucracy, and leaving the baseline unchanged would report an approved change as if it were a performance problem.
Question 3 of 10, Project Management Concepts. Choose 2.
Which roles typically sit on a project's change control board? (Choose two.)
- AThe vendor account manager who sold the tool
- BKey stakeholders affected by changes Correct answer
- CTesters who execute the system test cases
- DThe project sponsor or a delegate Correct answer
- EEvery end user of the final product
Answer and explanation: Change control boards usually include the sponsor or delegate and key stakeholders with authority over scope, cost, and schedule. All end users would make the board unmanageable, testers provide input on impact but do not hold decision authority, and a vendor's account manager has a commercial interest and no governance role.
Question 4 of 10, Project Life Cycle Phases
A software release passed all system tests, but during user acceptance testing, business users say a report does not match how the finance team actually closes the month. What does this MOST likely indicate?
- AThe system test cases were executed in the wrong environment by the testers
- BThe development team failed to follow the organization's secure coding and review standards
- CRequirements were not validated with the right business stakeholders Correct answer
- DThe change control board approved too many changes during the execution phase
Answer and explanation: Passing system tests but failing UAT usually means the product matches the documented requirements, but those requirements did not reflect real business needs, which points to poor validation with the right stakeholders. The wrong test environment, coding standards, and change approvals would not explain a mismatch with how finance actually works.
Question 5 of 10, Project Life Cycle Phases
A project manager realizes during execution that one approved requirement conflicts with a new company security standard. What is the BEST next step?
- AAsk the security team to grant a permanent exception without assessing the risk
- BDocument the conflict and raise a change request to align the requirement with the standard Correct answer
- CBuild the requirement as approved because the scope baseline takes precedence over standards
- DRemove the requirement from the solution without informing the business owner
Answer and explanation: Conflicts between approved scope and organizational policy should be documented and resolved through change control, usually by updating the requirement. Building something non-compliant creates risk, silent removal skips stakeholders, and permanent exceptions without assessment undermine security governance.
Question 6 of 10, Project Life Cycle Phases
A client wants a vendor to start work immediately on a data migration whose total scope is unclear. The client wants to pay only for the hours actually worked. Which contract type fits BEST?
- ATime and materials Correct answer
- BCost plus award fee
- CFirm fixed price
- DFixed price incentive fee
Answer and explanation: Time and materials contracts pay for actual hours and materials at agreed rates, which suits unclear scope and quick starts. Fixed price contracts require well-defined scope, an incentive fee adds performance targets on a fixed price, and cost-plus contracts reimburse costs plus a fee, which is more administrative than paying hourly rates.
Question 7 of 10, Tools and Documentation
Auditors ask a project team to prove that every approved requirement for a payroll system was designed, built, and tested. Which document provides this traceability?
- AQuality management plan with test strategy
- BRequirements traceability matrix Correct answer
- CProject charter
- DWork breakdown structure
Answer and explanation: A requirements traceability matrix links each requirement to its source, design elements, and test cases through the life cycle. The WBS decomposes deliverables but does not trace requirements to tests, the charter is high-level, and the quality management plan describes how testing will be done rather than proving each requirement was covered.
Question 8 of 10, Tools and Documentation. Choose 2.
A project manager must choose a collaboration platform for a project with external contractors. Which requirements should take priority? (Choose two.)
- ABuilt-in polls and reactions to make team discussions more engaging
- BSupport for guest access with permissions limited to project content Correct answer
- CThe lowest per-user price, even if guest access must be shared
- DCompliance with the organization's security and data retention policies Correct answer
- EAbility for any user to delete any file without leaving a version history
Answer and explanation: Controlled guest access and compliance with security and retention policies protect data while enabling collaboration with contractors. Polls and reactions are nice-to-have features, choosing on price alone when guest access must be shared weakens accountability, and unrestricted deletion without history creates data loss and audit risks.
Question 9 of 10, Basics of IT and Governance
Which statement BEST describes the shared responsibility model in cloud computing?
- AThe provider secures the infrastructure; the customer secures its data, access, and configuration Correct answer
- BThe provider and the customer each pay half of the cost of every security incident that occurs
- CThe provider is fully responsible for all security, including customer data and user access settings
- DThe customer is fully responsible for all security, including the physical data center facilities
Answer and explanation: Under shared responsibility, the provider secures the cloud infrastructure while the customer secures its data, identities, and configurations, with the split depending on the service model. The provider is not responsible for everything, the customer does not secure physical facilities, and the model is about duties rather than splitting costs.
Question 10 of 10, Basics of IT and Governance
A bank plans to roll out new teller software to one branch, evaluate the results for two weeks, and then roll it out to all other branches. Which deployment approach is this?
- ABlue-green deployment
- BBig bang deployment
- CParallel deployment
- DPilot deployment Correct answer
Answer and explanation: A pilot deploys to a small group first to validate the solution before a wider rollout. A big bang deployment switches everyone at once, a parallel deployment runs old and new systems side by side for the same users, and blue-green switches traffic between two identical production environments.