CTAL-TM

ISTQB Advanced Level Test Management (CTAL-TM) v3.0 practice exams

240 questions in 5 timed practice tests. Each test has about 50 questions and a 120-minute limit. The pass mark is 66%. Results are split across the 3 exam domains.

Exam at a glance

CTAL-TM practice exam settings
Practice tests 5
Questions in total 240
Questions per test About 50
Time limit per test 120 minutes
Pass mark 66%
Question types Single answer and multiple answer (36 multiple-answer questions)
Level Professional
Category Software Testing

These are the settings of our practice tests. Check the official ISTQB exam page for the current exam format before you book.

Domains and weights

CTAL-TM exam domains, weights and question counts
Domain Weight Weight bar Questions in our bank
Managing the Test Activities 52% 125
Managing the Product 30% 72
Managing the Team 18% 43

Sample questions

Question 1 of 3

An organisation's test policy states that testing must provide independent, objective information about product quality. A project manager proposes that developers perform all testing, including acceptance testing, to save cost. What should the test manager do FIRST?

  1. A Escalate immediately to senior management and suspend test planning until the project manager withdraws the proposal
  2. B Agree, but ask developers to swap modules with each other so that every developer reviews code they did not write
  3. C Point out the conflict with the test policy and propose a strategy that keeps suitable independence at the higher test levels (correct answer)
  4. D Accept the proposal, because test independence only matters in safety-critical projects and the test policy is guidance rather than binding
Why: The project test strategy must align with the organisation's test policy, so the test manager should show the conflict and propose a strategy with suitable independence, for example independent testers for system and acceptance testing. Treating the policy as optional ignores the organisational level that governs projects. Escalating and halting planning skips the first step of discussing the conflict. Swapping modules between developers adds a little independence but still conflicts with the policy for acceptance testing.

Question 2 of 3

A test manager on a regulated medical-device project must show auditors that every safety requirement has been covered by at least one executed test and that each failed test is linked to a defect report. Which test management practice BEST provides this evidence?

  1. A Running an exploratory testing session per safety requirement and archiving the signed session sheets in the project repository afterwards
  2. B Publishing a weekly test progress report that lists the percentage of test cases passed per test level
  3. C Adopting a regression-averse test strategy so that all safety tests are re-executed in every build
  4. D Maintaining bidirectional traceability between the test basis, test cases, test results and defect reports (correct answer)
Why: Bidirectional traceability links requirements to tests, results and defects, so coverage of each safety requirement and the defect behind each failure can be demonstrated in both directions. A pass-rate report shows progress but not per-requirement coverage. Session sheets document exploration but do not systematically prove coverage of every requirement. A regression-averse strategy addresses re-execution, not the audit link between requirements, results and defects.

Question 3 of 3

A product team moves from a yearly sequential release cycle to two-week iterations with continuous integration. Which change to test management is MOST appropriate?

  1. A Keeping a single master test plan approved at project start and running one system test phase before every yearly release
  2. B Replacing exit criteria with a fixed number of exploratory testing hours that is negotiated separately for each sprint
  3. C Planning per iteration under a lightweight release test plan, with automated regression tests in the CI pipeline (correct answer)
  4. D Moving all test analysis and design to a separate test team that starts after the final iteration has been completed
Why: In iterative development, test planning is done at release and iteration level, and fast feedback relies on automated regression tests in the CI pipeline. A single upfront master plan with one final system test phase reflects the sequential model being abandoned. Starting test work after the last iteration delays feedback and contradicts iterative delivery. Exploratory hours can complement, but they do not replace a definition of done or exit criteria.

What your score report looks like

Example attempt, CTAL-TM practice test 3

84%

Passed
Pass mark 66%

Score by exam domain
DomainWeightYour score%
Managing the Test Activities 52%
88
Managing the Product 30%
81
Managing the Team 18%
76

Study next: Managing the Team. It is below the pass mark and carries 18% of the exam.

Domains and pass mark from our CTAL-TM practice tests. Scores are an example attempt.

Study plans

Two weeks

  1. Day 1: take practice test 1 in exam mode to get a baseline.
  2. Days 2 to 5: domain mode on Managing the Test Activities and Managing the Product, the two most heavily weighted domains.
  3. Day 6: practice test 2 in exam mode, then the mistakes quiz.
  4. Days 7 to 12: practice tests 3 to 5, one every other day, each followed by its mistakes quiz.
  5. Days 13 and 14: final mode. Book the exam when your readiness stays above the pass mark.

Four weeks

  1. Week 1: one practice test in practice mode, reading every explanation. Note your two lowest domains.
  2. Week 2: domain mode on those two domains, then a second practice test in exam mode.
  3. Week 3: practice tests 3 and 4 in exam mode, with the mistakes and flagged quizzes after each.
  4. Week 4: practice test 5 and final mode until your readiness holds above the pass mark.

Questions about the CTAL-TM practice exams

Are these real CTAL-TM exam questions?
No. We write every question ourselves and map it to the published CTAL-TM exam objectives. We do not use leaked or recalled questions.
Do the time limit and pass mark match the official exam?
They match the settings of our practice tests. Exam providers change their format from time to time, so check the official exam page before you book.
Can I try it before I pay?
Yes. The free mini exam has 15 questions with full explanations and needs no account.
How long do I keep access?
A single-exam purchase gives you 12 months of access. All-Access includes this exam for as long as your subscription runs.
What happens after I finish a test?
You get a score, a pass or fail against the pass mark, a score per domain and every answer with its explanation.

Last updated November 2026. Written and reviewed by the DevOpsCode Lab team.

DevOpsCode Lab is not affiliated with ISTQB. CTAL-TM and related names are trademarks of their owners.

Related exams
Exam Vendor Level Questions Minutes Price
CT-AIISTQB Tester AI Testing (CT-AI) v2.0 ISTQB Specialty 200 60 $14.99
CTFLISTQB Tester Foundation Level (CTFL) v4.0 ISTQB Foundational 200 60 $9.99
CTFL-ATISTQB Tester Foundation Level - Agile Tester (CTFL-AT) ISTQB Foundational 200 60 $9.99