Question 1 of 10, People
A newly formed hybrid team includes members from three countries who have never worked together. During the first two weeks, several members say they are unsure how decisions get made and when they are expected to be online. What should the project manager do?
- AAsk each functional manager to brief their own staff on the working hours and decision rules they prefer to follow
- BPublish a RACI matrix so every member knows which deliverables they are accountable for and who must be consulted
- CSchedule a daily status meeting at a fixed headquarters time for all members
- DWork with the team to create a team charter covering decision rules, overlap hours, and communication norms Correct answer
Answer and explanation: A team charter, created with the team, establishes ground rules such as decision-making processes, core collaboration hours and communication norms, which is exactly what the members are missing. A RACI clarifies deliverable roles but not working agreements. Delegating to functional managers produces inconsistent rules across locations. A fixed headquarters meeting time ignores the time-zone problem and does not define how decisions are made.
Question 2 of 10, People
Two senior engineers on a hybrid data-center migration project argue openly in a stand-up about whether to migrate the storage layer before or after the network cutover. The disagreement is technical, both have valid points, and the decision is needed within a week. What should the project manager do FIRST?
- AAsk the sponsor to make the call so the team stops losing time to the dispute
- BPick the option proposed by the more experienced engineer and record the decision and rationale in the decision log
- CFacilitate a session where both engineers compare their options against agreed criteria such as risk Correct answer
- DPostpone the decision until the network cutover is complete, then reassess whether the storage order still matters
Answer and explanation: A collaborative, problem-solving approach that evaluates both options against shared criteria resolves the root issue and keeps both engineers engaged, which is the preferred conflict approach when time allows. Escalating to the sponsor gives away a decision the team can make itself. Choosing by seniority is forcing and ignores valid technical input. Postponing is withdrawal and the decision is needed before the cutover anyway.
Question 3 of 10, People
A project manager notices that a usually productive developer has missed two sprint commitments and has stopped speaking in retrospectives. Velocity for the rest of the team is unchanged. What is the BEST next step?
- ARaise the missed commitments in the next retrospective so that the whole team can agree on corrective actions
- BMeet privately with the developer to understand what is happening and how the project manager can support them Correct answer
- CInform the developer's functional manager about the performance drop so it is recorded before the appraisal cycle
- DReassign the developer's backlog items to other team members until their output returns to the previous level
Answer and explanation: A private, supportive conversation is the servant-leadership response and lets the project manager discover root causes such as workload, personal issues or impediments. Discussing an individual's performance in a retrospective could embarrass them and damage psychological safety. Going to the functional manager first skips direct engagement. Reassigning work treats the symptom and may further disengage the developer.
Question 4 of 10, Process
A stakeholder asks a team member to add a small reporting field to a deliverable that is already in the approved scope baseline. The team member agrees because it will take only an hour. What is the project manager's BEST response?
- AAsk the team member to log the hour as overtime so that the change does not affect the project cost baseline
- BAdd the field to the backlog for the next release so that it does not disturb the work currently in progress
- CExplain that any change to baselined scope goes through the change control process, then assess the request Correct answer
- DAllow the change because its effort is small and the stakeholder will be more satisfied with the deliverable
Answer and explanation: Unapproved additions to baselined scope are scope creep, even when small; the project manager guides the request through integrated change control so impacts are evaluated and the baseline stays valid. Accepting the change informally undermines control. Moving it to a backlog is an adaptive practice that still requires a decision on a predictive baseline. Hiding the effort as overtime distorts performance data.
Question 5 of 10, Process
A software vendor is building a custom integration for which the scope is unclear and is likely to change during development. The buyer wants to limit its cost risk while allowing flexibility. Which contract type is MOST appropriate?
- AFixed price with economic price adjustment clause
- BCost plus percentage of cost without any ceiling
- CTime and materials with a not-to-exceed ceiling Correct answer
- DFirm fixed price with a detailed statement of work
Answer and explanation: Time and materials suits uncertain scope, and a not-to-exceed ceiling caps the buyer's cost exposure. A firm fixed price requires well-defined scope; the vendor would add large contingencies or claim changes. Cost plus percentage of cost gives the seller an incentive to increase cost and is prohibited in many settings. Economic price adjustment addresses inflation over long contracts, not unclear scope.
Question 6 of 10, Process
A sponsor asks a project manager to choose a delivery approach for a new mobile banking feature. Requirements are expected to evolve based on customer feedback, but the regulatory security controls are fixed and must be approved before launch. Which approach is MOST appropriate?
- AA predictive approach with a full requirements baseline approved before any build
- BA hybrid approach: iterative delivery of features plus a predictive track for security approvals Correct answer
- CA purely adaptive approach where the security controls are added to the backlog and reprioritized every sprint
- DAn incremental approach that delivers the entire feature set in one release after the security review is done
Answer and explanation: Evolving customer requirements favour iterative delivery, while fixed regulatory controls with a formal approval gate fit a predictive track, so a hybrid tailoring is best. A fully predictive approach resists the expected change. Treating mandatory controls as reprioritizable backlog items risks non-compliance. A single release after review is not incremental and delays feedback.
Question 7 of 10, Process. Choose 2.
Which of the following are inputs a project manager should consider when deciding between building a component in-house and buying it? (Choose two.)
- AThe organization's in-house skills and capacity to build the component Correct answer
- BThe resource calendar of the procurement manager for the next quarter
- CThe seller's performance rating from the previous year's audits
- DThe total cost of ownership of each option, including maintenance Correct answer
- EThe project's quality metrics that were defined for the deliverables
Answer and explanation: Make-or-buy analysis compares total costs of each option, including ongoing costs, and considers whether the organization has the capability and capacity to build. A specific seller's audit history matters during source selection after deciding to buy. Quality metrics apply to deliverables regardless of source. A procurement manager's calendar does not drive the decision.
Question 8 of 10, Business Environment. Choose 2.
Midway through a merger integration project, the acquiring company changes its strategy to divest one of the business units the project was integrating. What should the project manager do? (Choose two.)
- APropose changes to the project through the governance process based on that assessment Correct answer
- BContinue integrating the business unit until the divestment is formally completed
- CTreat the change as an accepted risk and record it in the risk register only
- DStop work on all deliverables until a new charter is approved by the board
- EAssess with the sponsor which scope and benefits are affected by the strategy change Correct answer
Answer and explanation: When strategy changes, the project manager evaluates the impact on scope and benefits with the sponsor and then uses governance to realign the project, which may include changing or cancelling parts of it. Continuing unchanged wastes resources on work that no longer creates value. Stopping everything is excessive when only part of the scope is affected. The change has already happened, so it is an issue to act on, not a risk to accept.
Question 9 of 10, Business Environment
A risk has a 30 percent probability of causing a $50,000 delay penalty. A mitigation costs $6,000 and would reduce the probability to 10 percent. Based on expected monetary value, what should the project manager conclude?
- ADo not implement it, because a 10 percent chance of the penalty still remains
- BDo not implement it, because the $6,000 cost exceeds the residual expected loss of $5,000
- CImplement it, because the $6,000 cost is far lower than the full $50,000 penalty
- DImplement it, because expected loss falls by $10,000 for a $6,000 cost Correct answer
Answer and explanation: EMV before mitigation is 0.30 x 50,000 = $15,000 and after is 0.10 x 50,000 = $5,000, so the response cuts expected loss by $10,000 for $6,000 and is worthwhile. Comparing the cost with the residual expected loss ignores the reduction achieved. Comparing the cost with the full impact ignores probability. A remaining probability is normal and does not make a cost-effective response wrong.
Question 10 of 10, Business Environment
A project manager discovers that a team member has been sharing customer test data, which includes personal information, with an offshore contractor that has no data processing agreement. What should the project manager do FIRST?
- AAsk the team member to anonymize future extracts and keep the current incident within the team
- BAsk the contractor to delete the data and confirm deletion by email, then continue as before
- CRecord the event as a risk in the risk register and plan a response for the next phase
- DStop the data sharing and report the incident to the data protection or compliance function Correct answer
Answer and explanation: Unauthorized sharing of personal data is a compliance incident; the first steps are to contain it and report it through the organization's data protection process, which may have legal notification deadlines. Asking for deletion alone bypasses required reporting. It has already happened, so it is not a risk. Keeping it within the team conceals a potential breach.