Question 1 of 10, Part 1: Basic Concepts and General Definitions

Which TOGAF term refers to an ability that an organization, person or system possesses, typically expressed in general and high-level terms and requiring a combination of organization, people, processes and technology to achieve?

  1. ACapability Correct answer
  2. BBusiness function
  3. CBusiness service
  4. DValue stream

Answer and explanation: TOGAF defines capability as an ability an organization, person or system possesses, usually expressed at a high level and achieved by combining organization, people, process and technology. A business function delivers business capabilities aligned to an organization but is a unit of work, not the ability itself. A business service supports business capabilities through an explicitly defined interface, and a value stream is an end-to-end set of activities that creates an overall result for a stakeholder.

Question 2 of 10, Part 1: Basic Concepts and General Definitions. Choose 2.

Which TWO items are components of the Architecture Repository as described by the TOGAF Standard? (Choose two.)

  1. AThe Enterprise Stakeholder Map
  2. BThe Solutions Landscape Correct answer
  3. CThe Implementation Factor Catalog
  4. DThe Architecture Roadmap Register
  5. EThe Governance Log Correct answer

Answer and explanation: The Architecture Repository includes the Architecture Metamodel, Architecture Capability, Architecture Landscape, Standards Information Base, Reference Library, Governance Log, Architecture Requirements Repository and Solutions Landscape. The Implementation Factor Catalog is a migration planning technique output, not a repository component. No 'Architecture Roadmap Register' or 'Enterprise Stakeholder Map' is defined as a repository component, although roadmaps and stakeholder maps are stored as content.

Question 3 of 10, Part 1: ADM Phases and Applying the ADM

During Phase B, which sequence of steps does the ADM describe for developing the Business Architecture?

  1. ADefine work packages; estimate costs; prioritize projects; develop the Baseline description of business capabilities
  2. BSign the Architecture Contract; develop the Target description; perform compliance review; issue a Request for Architecture Work
  3. CSelect reference models, viewpoints and tools; describe Baseline and Target; analyze gaps; define candidate roadmap components Correct answer
  4. DPerform gap analysis; select reference models and tools; define Transition Architectures; obtain approval for the Statement of Architecture Work

Answer and explanation: Phases B, C and D share a common pattern: select reference models, viewpoints and tools; develop baseline and target descriptions; perform gap analysis; define candidate roadmap components; resolve impacts; review with stakeholders; finalize; and create the Architecture Definition Document. Gap analysis cannot precede the baseline and target descriptions. Architecture Contracts belong to Phase G, and work package costing and prioritization are Phase E and F activities.

Question 4 of 10, Part 1: ADM Phases and Applying the ADM

In an Architecture Development iteration, an organization chooses to describe the Baseline Architecture first and then derive the Target. Which situation would MOST justify this baseline-first approach?

  1. AThe organization wants a revolutionary redesign and does not want its existing assets and processes to influence its target thinking
  2. BThe current landscape is complex and poorly understood, so a shared baseline is needed before agreeing change Correct answer
  3. CThe sponsor has already approved a detailed target design and only needs the migration steps documented
  4. DThe architecture is for a greenfield business unit that has no existing processes or systems to describe

Answer and explanation: Baseline first is appropriate when the existing environment is complex, poorly understood or not agreed, because a shared understanding of today must be built before planning change. When a revolutionary target is wanted, TOGAF suggests target first so existing assets do not constrain thinking. If the target is already detailed or there is no baseline at all, as in a greenfield unit, starting with the baseline adds little value.

Question 5 of 10, Part 1: ADM Techniques, Governance and Architecture Content

A delivery project implements every feature in the architecture specification, but also adds some features that are not in accordance with it. Which compliance level applies?

  1. ANon-conformant
  2. BCompliant
  3. CFully Conformant
  4. DConformant Correct answer

Answer and explanation: Conformant means all specification features are implemented in accordance with it, but extra features exist that are not in line with the specification. Compliant means only part of the specification is implemented, all correctly. Fully Conformant requires full correspondence with nothing extra, and Non-conformant means some implemented features are not in accordance with the specification itself.

Question 6 of 10, Part 1: ADM Techniques, Governance and Architecture Content

During a compliance review, every feature an implementation contains is covered by and in line with the architecture specification, but some specified features have not been implemented yet. Which compliance level applies?

  1. ACompliant Correct answer
  2. BConformant
  3. CConsistent
  4. DFully Conformant

Answer and explanation: Compliant means some features of the specification are not implemented, but everything that is implemented is in accordance with the specification. Conformant means all features in the specification are implemented, though some extra features are not in line with it. Fully Conformant is full correspondence with nothing extra, and Consistent means implemented features match the specification but some specification features are not implemented and others are implemented outside its scope.

Question 7 of 10, Part 2: Preliminary Phase, Phase A and Stakeholder Management

A regional hospital group has merged three trusts, each with its own small architecture team and its own informal methods. The new CIO wants a single enterprise architecture practice before launching any transformation projects. As lead architect, what is the BEST next step according to the TOGAF Standard?

  1. AStart Phase A immediately for the largest planned project and let the merged practice emerge from the lessons of that first engagement
  2. BAsk each former trust team to continue with its own method and integrate the results later in Phase H, once the first change requests arrive
  3. CRun the Preliminary Phase to agree the EA organizational model, tailored framework, principles and governance for the group Correct answer
  4. DSelect an architecture tool and populate the repository with all existing diagrams so a baseline is available before any governance is agreed

Answer and explanation: When the architecture capability itself is fragmented, TOGAF's Preliminary Phase is where the organizational model, tailored framework, principles and governance are established, so later ADM cycles run on a common footing. Jumping to Phase A for a single project leaves the capability undefined and the results inconsistent. Letting three methods continue defers integration until problems surface, and loading a tool before agreeing governance and the metamodel produces an unstructured repository.

Question 8 of 10, Part 2: Phases B-D Architecture Development

A telecom operator's architect is pressed to skip formal stakeholder reviews at the end of Phases B, C and D to save time. What is the MOST likely consequence, based on TOGAF?

  1. AArchitectures may proceed to planning without stakeholder agreement, increasing the risk of rework and resistance later Correct answer
  2. BNothing changes, because the Statement of Architecture Work already guarantees that every stakeholder accepts the result
  3. CThe ADM cycle will be reclassified as a Phase H change, which removes the need for any stakeholder review
  4. DThe Architecture Board will automatically approve the architecture, since reviews are only required for strategic architectures

Answer and explanation: TOGAF includes a formal stakeholder review in each of Phases B to D to confirm the architecture meets its motivation; skipping it risks moving forward without agreement and facing rework and resistance. Board approval is not automatic and reviews apply to all levels. The Statement of Architecture Work defines the project but does not guarantee acceptance, and skipping reviews does not change the cycle into Phase H.

Question 9 of 10, Part 2: Phases E-H, Implementation Governance and Change. Choose 2.

Which TWO outputs are typical of Phase H: Architecture Change Management? (Choose two.)

  1. AConsolidated Gaps, Solutions and Dependencies Matrix
  2. BArchitecture updates and changes to the architecture framework and principles Correct answer
  3. CNew Request for Architecture Work to initiate another ADM cycle Correct answer
  4. DApproved Organizational Model for Enterprise Architecture
  5. EDraft Architecture Vision for the current cycle

Answer and explanation: Phase H outputs include architecture updates, changes to the framework and principles, a new Request for Architecture Work, and updated Statements of Architecture Work, Architecture Contracts and Compliance Assessments. The Organizational Model for EA is a Preliminary Phase output. The Architecture Vision is produced in Phase A, and the consolidated gaps matrix is a Phase E technique.

Question 10 of 10, Part 2: Risk, Security and Architecture Governance in Practice

A retailer's Phase D design introduces a new payment gateway. The security architect asks how to make sure security requirements are traced into implementation. Which approach BEST fits TOGAF?

  1. ADocument them only in the vendor's statement of work, since the gateway vendor is responsible for security
  2. BRecord them as Architecture Principles so they do not need to be checked during implementation
  3. CPut them in the Architecture Requirements Specification and verify them via compliance reviews and contracts Correct answer
  4. DLeave them to the operations team to configure after go-live, as security is an operational matter

Answer and explanation: Security requirements, like other architecture requirements, belong in the Architecture Requirements Specification and are verified through Phase G compliance reviews and Architecture Contracts. A vendor statement of work is not the architecture's control point. Principles guide decisions but do not replace specific verifiable requirements, and deferring security to after go-live misses design-time controls.